Schedule
| 1 May 2026 | Agree final roadmap (this document). |
| 1 Aug 2026 | All major features should be merged into master. |
| 1 Sep 2026 | Feature freeze. |
| 20 Sep 2026 | String freeze. |
| 4 Oct 2026 | Final release.* whoosh!! |
Policy changes
Project governance
At present, we use a benevolent dictator model. The BD defines the project's strategic direction and has the final say in decisions.
Dependency upgrades
Database model changes
Are there features that require database change? This should happen in the beginning of the development cycle. List your requirements here.
- ...
Major goals
This section lists main goals developers want to achieve. Major goals should be started in a GEPS branch. Major goals require a developer and a reviewer.
- ....
Minor goals
This section lists minor goals developers want to achieve. Minor goals can be done by one developer alone.
- ....